Richfield High School
Completed week ending Friday, May 7, 2021
- Testing, balancing, and commissioning of HVAC system continued
Planned week ending Friday, May 14, 2021
- Continue to test, balance, and commission the HVAC system
- Install fencing at loading dock and courtyard mechanical equipment
Centennial Elementary
Completed week ending Friday, May 7, 2021
- Contractors continued to address items noted on the IEA Commissioning Log
Planned week ending Friday, May 14, 2021
- IEA Commissioning to continue verifying completed commissioning log items
- Contractors to continue to address items noted on the IEA Commissioning Log
Sheridan Hills Elementary
Completed week ending Friday, May 7, 2021
- Continued the installation of the controls for the new chiller unit
- Began flushing and filling the chilled water system in preparation of chiller unit startup
- Removed scaffold used for masonry installation at the Kitchen/Receiving addition
Planned week ending Friday, May 14, 2021
- Complete the installation of the controls for the new chiller unit
- Complete chiller unit start-up
Richfield Middle School
Completed week ending Friday, May 7, 2021
- Continued design of the Best Buy Teen Tech Center
- Sheetrock, taping, and mudding continued in the administration reception space
- Wood shop equipment was delivered and placed
Planned week ending Friday, May 14, 2021
- Meeting with Best Buy to review design progress for Teen Tech Center
- One hour power outage for electrical transformer and panel work
- Prep work for dishwasher and boiler room for boiler shutdown
- Finish ceiling grid and pad in administration space
- Install mechanical diffusers, registers, and lights in ceiling of administration space
- Casework installation begins in administration space
- Hydronic piping in lower-level tunnels
Richfield STEM Elementary
Completed week ending Friday, May 7, 2021
- Installed gate and finish fence around the mechanical condensing unit
- Commissioning
Planned week ending Friday, May 14, 2021
- Chiller preparation and start up
- Commissioning
Richfield Community Education - Central Education Center
Completed week ending Friday, May 7, 2021
- Continued mechanical and electrical rough-in in the Admin space and Area D Offices
- Continued taping and sanding drywall in the Admin space and Area D Offices
- Continued plaster patching existing plaster walls
- Began tile installation in the Area multi-user Toilet rooms
- Completed the demolition of the existing exterior doors and frame at the new secure vestibule location
Planned week ending Friday, May 14, 2021
- Complete taping and sanding drywall in the Admin space and Area D Offices
- Begin painting walls in the Admin space and Area D Offices
- Continue tile installation in the Area A multi-user Toilet rooms
- Begin aluminum storefront installation at the new secure vestibule entrance
- Complete concrete slab moisture mitigation in the Admin space
- Begin acoustical ceiling grid in Admin space and Area D Offices