ICS Weekly Report: May 7, 2021

Decorative image with colored diamonds on gray background
ICS Weekly Report: May 7, 2021

Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

Richfield High School

Completed week ending Friday, May 7, 2021  

  • Testing, balancing, and commissioning of HVAC system continued

Planned week ending Friday, May 14, 2021  

  • Continue to test, balance, and commission the HVAC system
  • Install fencing at loading dock and courtyard mechanical equipment

Centennial Elementary

Completed week ending Friday, May 7, 2021   

  • Contractors continued to address items noted on the IEA Commissioning Log

Planned week ending Friday, May 14, 2021  

  • IEA Commissioning to continue verifying completed commissioning log items
  • Contractors to continue to address items noted on the IEA Commissioning Log

Sheridan Hills Elementary

Completed week ending Friday, May 7, 2021  

  • Continued the installation of the controls for the new chiller unit
  • Began flushing and filling the chilled water system in preparation of chiller unit startup
  • Removed scaffold used for masonry installation at the Kitchen/Receiving addition

Planned week ending Friday, May 14, 2021  

  • Complete the installation of the controls for the new chiller unit
  • Complete chiller unit start-up

Richfield Middle School

Completed week ending Friday, May 7, 2021  

  • Continued design of the Best Buy Teen Tech Center
  • Sheetrock, taping, and mudding continued in the administration reception space
  • Wood shop equipment was delivered and placed

Planned week ending Friday, May 14, 2021  

  • Meeting with Best Buy to review design progress for Teen Tech Center
  • One hour power outage for electrical transformer and panel work
  • Prep work for dishwasher and boiler room for boiler shutdown
  • Finish ceiling grid and pad in administration space
  • Install mechanical diffusers, registers, and lights in ceiling of administration space
  • Casework installation begins in administration space
  • Hydronic piping in lower-level tunnels

Richfield STEM Elementary

Completed week ending Friday, May 7, 2021  

  • Installed gate and finish fence around the mechanical condensing unit
  • Commissioning

Planned week ending Friday, May 14, 2021  

  • Chiller preparation and start up
  • Commissioning

Richfield Community Education - Central Education Center

Completed week ending Friday, May 7, 2021  

  • Continued mechanical and electrical rough-in in the Admin space and Area D Offices
  • Continued taping and sanding drywall in the Admin space and Area D Offices
  • Continued plaster patching existing plaster walls
  • Began tile installation in the Area multi-user Toilet rooms
  • Completed the demolition of the existing exterior doors and frame at the new secure vestibule location

Planned week ending Friday, May 14, 2021  

  • Complete taping and sanding drywall in the Admin space and Area D Offices
  • Begin painting walls in the Admin space and Area D Offices
  • Continue tile installation in the Area A multi-user Toilet rooms
  • Begin aluminum storefront installation at the new secure vestibule entrance
  • Complete concrete slab moisture mitigation in the Admin space
  • Begin acoustical ceiling grid in Admin space and Area D Offices

Download PDF Report

Read More

2023 graduate holding diploma

The Minnesota Department of Education released the 2023 graduation rates. We are excited to share that we have made consistent gains in many areas and that Richfield High School’s four-year graduation rate (94.1%) exceeds the statewide graduation rate of 83.3% by 10.8 percentage points. 

Empty Bowls Fundraiser: You're Invited

You’re invited to join us from 5-6:30 p.m. on Tuesday, March 12, for the Empty Bowls fundraiser. Empty Bowls is an event celebrating our community through art, music and food!