ICS Weekly Report: May 21, 2021

Decorative image with colored diamonds on gray background

Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

Richfield High School

Completed week ending Friday, May 21, 2021

  • Minor warranty and punch list work reviewed and completed
  • Chiller/cooling system start up

Planned week ending Friday, May 28, 2021

  • Commissioning of chiller/cooling system to take place

Centennial Elementary

Completed week ending Friday, May 21, 2021

  • ICS continued to coordinate with the contractors and the Owner’s commissioning agent in the effort of closing out the last remaining open Commissioning Log items.
  • District Facilities personnel started up the chiller to begin cooling the building. A few issues with the equipment were identified and addressed by the contractors involved with the installation.

Planned week ending Friday, May 28, 2021

  • IEA Commissioning tentatively planned to begin commissioning of the HVAC cooling system.

Sheridan Hills Elementary

Completed week ending Friday, May 21, 2021

  • Continued insulation of the chilled water system
  • Continued installation of the chiller system controls
  • Owner’s abatement contractor began the demolition of the (2) existing steam boilers

Planned week ending Friday, May 28, 2021

  • Continued preconstruction coordination with the contractor and District staff in preparation of the upcoming summer renovation phase
  • Continue insulation of the chilled water system
  • Continue installation of the chiller system controls

Richfield Middle School

Completed week ending Friday, May 21, 2021

  • Abatement in tunnels, lower level, and boiler room
  • Boiler room demolition
  • Flooring in administration spaces
  • Millwork in administration spaces
  • Finishes in nurses’ restroom
  • HVAC and mechanical equipment startup

Planned week ending Friday, May 28, 2021

  • Cleaning in administration space.
  • Punch list
  • Testing and balancing of HVAC system
  • Continue boiler room demolition

Richfield STEM Elementary

Completed week ending Friday, May 21, 2021

  • Punch list items
  • Started up chiller

Planned week ending Friday, May 28, 2021

  • Test, balance and commission chiller

Central Education Center

Completed week ending Friday, May 21, 2021

  • Continued mechanical and electrical rough-in in the Admin space and Area D offices.
  • Completed tile installation in the Area A Toilet Rooms.
  • Continued painting walls and door frames in the Admin space and Area D offices.
  • Completed aluminum storefront installation at the new Main Entry/Reception areas.
  • Continued ACT ceiling grid installation in the Admin space and Area D offices.
  • Completed the epoxy moisture mitigation installation in the Admin space.
  • Owner’s abatement contractor began striping insulation off the mechanical piping in the tunnel areas.
  • ICS conducted a pre-con meeting with the contactor and the Owner’s abatement contractor in preparation of the next phase of construction.
  • ICS conducted a walkthrough with All Furniture and District staff in preparation of the packing and moving required for next phase of construction.

Planned week ending Friday, May 28, 2021

  • Begin wall tile installation in the Area A corridor.
  • Complete painting walls in the Admin space and Area D offices.
  • Complete ACT ceiling grid installation in the Admin space and Area D offices. Begin the installation of new lights and mechanical grilles and diffusers in the Admin space and Area D offices.
  • Begin casework installation in the Admin space and Area D offices.
  • Begin mechanical piping demolition in the tunnel areas.

Download the PDF Report