Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page.
*This report is submitted from ICS on a weekly basis.
Richfield High School
Completed week ending Friday, July 23, 2021
- Continued financial and administration closeout
Planned week ending Friday, July 30, 2021
- Commissioning meeting to discuss open items
- Terrazzo floor patching
- Start preparation for competition gym restriping and logo painting
Centennial Elementary
Completed week ending Friday, July 23, 2021
-
Continued continued to address open commissioning log items
Planned week ending Friday, July 30, 2021
- Contractors to continue addressing open commissioning log items
Sheridan Hills Elementary
Completed week ending Friday, July 23, 2021
- Lower Level
- Continued installing plumbing and hydronic piping
- Classroom Wings
- Completed moisture mitigation for new flooring
- Continued aluminum storefront installation at the entrances/exits
- Kitchen/Cafeteria/Receiving
- Continued underground plumbing in the Kitchen
- Completed metal stud wall framing in the Receiving addition
Planned week ending Friday, July 30, 2021
- Lower Level/Tunnels
- Continue installing plumbing and hydronic piping
- Complete aluminum storefront installation at the entrances/exits
- Begin metal stud wall framing at classroom plumbing walls
- Begin flooring installation in the classrooms
- Kitchen/Cafeteria/Receiving
- Complete underground plumbing rough-in
- Complete concrete slab infills
- Complete structural steel erection
- Begin masonry walls and metal stud partitions in the Kitchen
Richfield Middle School
Completed week ending Friday, July 23, 2021
- Front Entrance
- Started installing ceiling grid
- Continued painting
- Started installing storefront
- Cafeteria-Dishwashing area
- Started cafeteria floor tile
- Poured back concrete floor
- Bathrooms
- Install ceiling grid
- 2nd Level Breakout Room-3rd Level Classroom
- Taped, mad, drywall finished in breakout rooms
- Finished mechanical and electrical rough in at 3rd level classroom
- Boiler Room
- Continued to install boiler, water heater, and pump piping
- Best Buy Teen Tech Center-Music Suite-Educational Pathways
- In wall mechanical and electrical rough ins
- Drywall
Planned week ending Friday, July 30, 2021
- Front Entrance
- Finish ceiling grid
- Install light fixtures, diffusers
- Cafeteria-Dishwashing Area
- Install dishwashing area floor tile
- Bathrooms
- Start wall and floor tiling
- 2nd Level Breakout Room-3rd Level Classroom
- Paint breakout rooms
- Ceiling grid
- Boiler Room
- Continue to install boiler, water heater, and pump piping
- Best Buy Teen Tech Center-Music Suite-Educational Pathways
- Finish drywall, tape, mudding
Richfield STEM Elementary
Completed week ending Friday, July 23, 2021
- Continued commissioning of chiller/cooling system took place
Planned week ending Friday, July 30, 2021
- 11-month warranty walkthrough to take place
- Continue commissioning items
Central Education Center
Completed week ending Friday, July 23, 2021
- Administration Spaces and Area D Offices
- Completed finned tube radiation installation
- Completed acoustical ceiling tile installation
- Completed final mechanical connections to AHU-4
- Classroom Wings
- Continued prepping floors for tile installation
- Continued framing metal stud walls, in-wall plumbing and electrical rough-in and hanging drywall
- Continued creating roof openings for new mechanical equipment
- Sitework/Chiller Enclosure
- Continued backfilling at the chiller enclosure and prep work for chiller pad
Planned week ending Friday, July 30, 2021
- Administration Spaces and Area D Offices
- Complete flooring installation
- Schedule punchlist walkthrough
- Classroom Wings
- Begin taping and sanding drywall
- Begin tile work in the Toilet rooms
- Continue mechanical and electrical rough-ins in the classrooms
- Continue creating roof openings for new mechanical equipment
- Sitework/Chiller Enclosure
- Complete concrete chiller pad and new sidewalks