ICS Weekly Report: July 16, 2021

Decorative image with colored diamonds on gray background
ICS Weekly Report: July 16, 2021

Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

Richfield High School

Completed week ending Friday, July 16, 2021

  • Biweekly meeting on open commissioning items was held
  • Meeting took place with LS Black to review final outstanding costs
  • Meeting to review Chiller Unit and roof screens took place

Planned week ending Friday, July 23, 2021

  • Continue financial and administration closeout

Centennial Elementary

Completed week ending Friday, July 16, 2021

  • Continued commissioning of the chiller/cooling system

Planned week ending Friday, July 23, 2021

  • Contractor to address issues identified on the commissioning issues log

Sheridan Hills Elementary

Completed week ending Friday, July 16, 2021

  • Lower Level
    • Continued plumbing and hydronic piping installation
  • Classroom Wings
    • Continued overhead electrical rough-in in the corridors
    • Completed interior vestibule storefronts at the entrances
    • Continued duct work installation in the B-wing classrooms and corridor
  • Kitchen/Cafeteria/Receiving
    • Began underground plumbing in the Kitchen/Cafeteria
    • Completed the new concrete slab in the Receiving addition
    • Began installing the new built-up roofing

Planned week ending Friday, July 23, 2021

  • Lower Level
    • Continue plumbing and hydronic piping installation
    Classroom Wings
    • Complete exterior storefronts install at the entrances
    • Continued overhead electrical rough-in in the corridors
    • Flooring contractor to mobilize and begin removing existing glue and mastic residue
    • Begin framing plumbing walls in the classrooms
  • Kitchen/Cafeteria/Receiving
    • Complete underground plumbing
    • Begin concrete infills at underground plumbing trenches

Richfield Middle School

Completed week ending Friday, July 16, 2021

  • Front Entrance
    • Started painting
    • Installed unit heaters
  • Cafeteria-Dishwashing area
    • Finished underground plumbing
    • Poured back concrete floor
  • Bathrooms
    • Start mechanical rough ins
  • Corridors 
    • Finished ceiling grid and light fixtures
  • 2nd Level Breakout Room-3rd Level Classroom
    • Drywall framing on 2nd level breakout rooms
    • Mechanical and electrical rough in for 3rd level classroom
  • Boiler Room
    • Installed doors and frames in boiler room
    • Continued to install boiler piping
  • Best Buy Teen Tech Center-Music Suite-Educational Pathways 
    • Demolition
    • Wall and window framing

Planned week ending Friday, July 23, 2021

  • Front Entrance
    • Start installing ceiling grid
    • Continue painting
    • Start installing storefront
  • Cafeteria-Dishwashing area
    • Install floor tile
  • Bathrooms
    • Wall framing
  • 2nd Level Breakout Room-3rd Level Classroom
    • Tape, mud, drywall finishes in breakout rooms
    • Finish mechanical and electrical rough in at 3rd level classroom
  • Boiler Room
    • Continue to install boiler, water heater, and pump piping
  • Best Buy Teen Tech Center-Music Suite-Educational Pathways 
    • In wall mechanical and electrical rough ins

Richfield STEM Elementary

Completed week ending Friday, July 16, 2021

  • Continued commissioning of chiller/cooling system took place

Planned week ending Friday, July 23, 2021

  • Continued commissioning of chiller/cooling system

Central Education Center

Completed week ending Friday, July 16, 2021

  • Administration Spaces and Area D Offices
    • Continued finned tube radiation installation
  • Classroom Wings
    • Began wall framing in the classrooms and toilet rooms
    • Began prepping floors and walls for tile installation
  • Sitework/Chiller Enclosure
    • Completed footings and foundations at the Chiller enclosure
    • Began backfilling at the chiller enclosure and prep work for new sidewalk

Planned week ending Friday, July 23, 2021

  • Administration Spaces and Area D Offices
    • Complete acoustical ceiling tiles
    • Complete flooring installation
  • Classroom Wings
    • Continue mechanical and electrical rough-in
    • Begin creating roof openings for new mechanical equipment
    • Begin taping and sanding drywall
    • Begin tile work in the Toilet rooms
  • Sitework/Chiller Enclosure
    • Finish prepping and pour new sidewalks

Download the PDF Report

Read More

2023 graduate holding diploma

The Minnesota Department of Education released the 2023 graduation rates. We are excited to share that we have made consistent gains in many areas and that Richfield High School’s four-year graduation rate (94.1%) exceeds the statewide graduation rate of 83.3% by 10.8 percentage points. 

Empty Bowls Fundraiser: You're Invited

You’re invited to join us from 5-6:30 p.m. on Tuesday, March 12, for the Empty Bowls fundraiser. Empty Bowls is an event celebrating our community through art, music and food!