ICS Weekly Report: August 7, 2020

Decorative image with colored diamonds on gray background
ICS Weekly Report: August 7, 2020

Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

Centennial Elementary

Completed week ending Friday, August 7, 2020

  • Completed setting rooftop mechanical units.
  • Completed tilework in the Area A mulit-user Toilet Rooms.
  • Continued casework and flooring installation in the perimeter classrooms.
  • Completed drywall installation in the Kitchen area and started quarry tile installation.
  • Completed drywall taping in the Admin Office area.
  • Completed mechanical and electrical ceiling finishes in the Resource Area.
  • Conducted a partial mechanical punchlist of Area A.

Planned week ending Friday, August 14, 2020

  • Continue casework and flooring installation in the perimeter classrooms.
  • Install acoustical ceilings and toilet partitions in the Area A multi-user Toilet Rooms.
  • Complete tilework in the Area B multi-user Toilet Rooms and begin plumbing fixtures.
  • Complete the installation of the acoustical ceiling grid and begin mechanical/electrical ceiling finishes in the Media Center area.
  • Complete wall paint and acoustical ceiling grid in the Admin Office area.
  • Begin conducting architectural punchlist walks of Area A.
  • Install aluminum storefront at the new secure entry.
  • Complete floor and wall tile in the Kitchen area.

Richfield Middle School

Completed week ending Friday, August 7, 2020

  • Installed glass and ceiling grid in Media Center
  • Continued painting and unit ventilator installation on third level and second level
  • Continued classroom carpet on third and second level
  • Tiled staff bathrooms on second level
  • Mechanical and electrical rough ins on main level
  • Installed structural steel for roof top units
  • Casework installation throughout
  • Continued ceiling grid throughout

Planned week ending Friday, August 14, 2020

  • Start painting on main level
  • Start tiling staff bathrooms on main level
  • Continue casework installation throughout
  • Finish flooring on second floor classrooms
  • Start installing doors throughout
  • Continue ceiling grid and lights on second floor
  • Start ceiling grid on main level
  • Speaker installation throughout
  • Ceiling pad installation on 3rd floor
  • Start cleaning on 3rd floor

Sheridan Hills Elementary

Completed week ending Friday, August 7, 2020

  • Completed all required moisture mitigation and floor leveling.
  • Completed the final connections to the unit ventilators in Area C classrooms.
  • Started tilework installation in all restrooms.
  • Began painting in the Admin Office area.
  • Completed acoustical ceiling grid in much of the C-wing and nearing completion of mechanical and electrical ceiling finishes.
  • Completed metal stud framing at the Front Entry corridor.

Planned week ending Friday, August 14, 2020

  • Complete wall paint and acoustical ceiling grid in the Admin Office area.
  • Complete tilework in the C-wing multi-user Toilet Rooms and begin plumbing fixture installation.
  • Begin flooring installation in C-wing i.e. SPED area and Level 2 classrooms.
  • Begin casework installation in the SPED area and Level 2 classrooms.
  • Complete electrical homerun connections at the panels.
  • Complete drywall installation and taping at the Front Entry corridor.
  • Complete metal stud framing and sheathing at the Front Entry addition.

Richfield High School

Completed week ending Friday, August 7, 2020

  • Boiler Room
    • Continue boiler connections
  • Area P Link
    • Continued mechanical and electrical rough ins
    • Started drywall on first and second level
    • Continued exterior finish system
  • Area D Main Lower Level Classroom
    • Ceiling and flooring installation
  • Lower Level Area F Dance Studio and Weight Room
    • Framed walls for offices
  • 2nd and 3rd level science rooms
    • Continued plumbing installation
  • New Athletics Commons and concessions
    • Finished wall tile work
    • Continued fin tube installation
    • Installed tile floor in concessions
  • New Athletic Corridor/Elevator
    • Above grade masonry
  • Main Gym
    • Continued wood flooring installation
  • Area A & B Art, FACS and Shop Classes
    • Continue casework installation
    • Continued flooring and ceilings
    • Mechanical and electrical finishes
  • Loading Dock
    • Pour concrete walls and dock level
  • Exterior Work
    • District parking lot grading
    • Continued irrigation at front entrance

Planned week ending Friday, August 14, 2020

  • Boiler Room
    • Continue boiler connections
  • Area P Link
    • Continue mechanical and electrical rough ins
    • Continue drywall framing
    • Finish exterior finish system
  • Area D Main Lower Level Classroom
    • Install doors and hardware
  • Lower Level Area F Dance Studio and Weight Room
    • Start prepping for flooring
  • 2nd and 3rd level science rooms
    • Continue casework and plumbing installation
  • New Athletics Commons and concessions
    • Install ceiling mechanical and electrical finishes and ceiling pad
    • Install concessions food equipment
  • New Athletic Corridor/Elevator
    • Above grade masonry
  • Main Gym
    • Finish wood flooring installation
    • Seal floor
  • Area A & B Art, FACS and Shop Classes
    • Continue casework installation
    • Continue flooring and ceilings
    • Mechanical and electrical finishes
  • Loading Dock
    • Backfill soil and dirt at retaining wall
  • Exterior Work
    • Continue district parking lot grading and start concrete curbing
    • Start landscaping at front entrance and courtyard

Richfield STEM Elementary

Completed week ending Friday, August 7, 2020

  • Finished flooring at main entrance
  • Continued dishwash equipment connections and installed fire system
  • Started ceiling grid in kitchen and dishwash area
  • Sprinkler work in dishwash area
  • Continued boiler room work
  • Installed sinks at Pre-kindergarten classrooms
  • Continued punch list, wall and floor patching
  • Corridor wall covering

Planned week ending Friday, August 14, 2020

  • Finish ceiling and final dishwasher connections
  • Final clean and health inspection in kitchen
  • Continue boiler room mechanical piping
  • Install interior window glazing throughout offices
  • Sod restoration
  • Exterior Louver installation throughout
  • Continue punch list o Final clean

Richfield Dual Language School

Completed week ending Friday, August 7, 2020

  • Contractors continued working to address punch list items.
  • ICS Commissioning continued performing the commissioning of the building’s mechanical and HVAC systems.

Planned week ending Friday, August 14, 2020

  • Contractors to continue working to address punch list items.
  • Contractors to continue working to address items noted on the commissioning corrective action log.

Download PDF Report

Read More

2023 graduate holding diploma

The Minnesota Department of Education released the 2023 graduation rates. We are excited to share that we have made consistent gains in many areas and that Richfield High School’s four-year graduation rate (94.1%) exceeds the statewide graduation rate of 83.3% by 10.8 percentage points. 

Empty Bowls Fundraiser: You're Invited

You’re invited to join us from 5-6:30 p.m. on Tuesday, March 12, for the Empty Bowls fundraiser. Empty Bowls is an event celebrating our community through art, music and food!